Truck accessBuilding the lane firstOntario

Will a Concrete Truck Get Up My Driveway?

The driveway that suits your car is not the driveway your house gets built from. Concrete, lumber, trusses and a crane all come up the same lane, and they are heavy, wide and tall.

Updated November 2026 · Georgian Bay Siteworks, the site work division of ICFHome.ca

Insured to $2,000,000Site work division of ICFHome.caBuilding since 1979250+ projects in Simcoe County
Quick answer: a loaded ready-mix truck weighs well over 20 tonnes. To carry it your lane needs a real granular base, a culvert that will not crush, room to pass between the trees, clearance overhead and somewhere to turn around. If it cannot be done, a concrete pump can reach from the road, at a price.

The five things that stop a truck

ProblemWhat happensFix
Soft baseThe truck sinks, and now you are paying for a tow300 mm or more of Granular B under 150 mm of Granular A for a construction lane
Weak or shallow culvertIt crushes on the first loadThe right pipe at the right depth
Too narrow or too tightMirrors and barkClear the corridor and ease the bends
Low branches and wiresThe truck stops at the roadTrim before delivery day
Too steepLoaded trucks spin, especially when wetRegrade, or pump from below

Base depths from our gravel driveway calculator. Culverts: driveway culvert cost.

Gravel driveway built to a new home through a wooded lot
Gravel driveway built to a new home through a wooded lot.

Build the lane before the hole

The driveway base goes in early, before excavation, so every truck after that has something to drive on. The finish course waits until the heavy traffic is done. That is the order in raw land to footings.

Half-load season

For several weeks each spring, many local roads are limited to about half the normal axle load. A full concrete truck is not allowed on them, whatever your driveway can carry. Plan pours around it. See half-load season dates.

When a truck simply cannot get there

A concrete pump moves concrete through a boom or a hose from where the truck can park. It adds cost and it has to be booked with the pour. On steep, tight or waterfront lots it is often the only way, so find out before pour day. See building on a steep lot.

Frequently Asked Questions

How much does a concrete truck weigh?

A loaded ready-mix truck weighs well over 20 tonnes.

Will a concrete truck damage my driveway?

On a thin gravel driveway over topsoil, yes. A proper base built for construction traffic carries it.

Can concrete be delivered in spring?

It depends on the road. During half-load season many roads cannot take a full truck.

Did Not Find Your Question?

Call 705-533-1633 or send us the address and what you are planning. We answer the phone, and we give prices in writing.